- Advise the client as to his responsibilities under CDM regulations 2015
- Ensure the designer has understood the risks in the design by designing out risks as far as practicable
- Ensure that pre- construction information is obtained from the client to make available to prospective contractors tendering for the work
- Vet prospective contractors for the client, so as to assure the client of their competence
- Assure the client that the principal contractor has raised a suitable construction phase plan prior to the start of the project
- Assure the client that the welfare facilities are adequate for workers prior to the start of the project
- Attend design meetings during the construction phase to ensure that risks are being managed satisfactorily, and advise the client accordingly
- Arrange for a Health and Safety File to be compiled and passed to the client at the end of the project
Under the Construction Design and Management Regulations 2015